Final test & Certificate
Step 1 / 2·Final test (10 questions)
0/2 steps done
Learning objectives — after this module you will:
- Consolidate the whole course
- Score 8/10 to unlock the certificate
Final test (10 questions)
You need at least 8 correct to pass.
How it works
Answer all 10 questions then click 'Submit'. You need at least 8/10. If you don't pass, review the explanations and retry — your best score is always kept.
Test: Stakeholder Management
Choose the best answer for each question.
To pass: at least 8 of 10 correct.
Question 1. What's the most common reason a good proposal gets blocked?
Question 2. On the power × interest grid, how should you treat someone with high power but low interest?
Question 3. Who is the 'blocker' in a decision?
Question 4. What's the difference between a position and an interest?
Question 5. Which question is most effective at surfacing a real interest?
Question 6. How should the 'what they get' line of a stakeholder card be written?
Question 7. What does the 'no surprises' rule mean?
Question 8. What should you ask for in your first private meeting with a key stakeholder?
Question 9. Of the four causes of objection, which one is solved by adding data?
Question 10. When two important stakeholders want opposite things, what should you do?